Football Stadium Benghazi Libya 2008
2008 NUSSLI received the order to realize a representative football stadium in Benghazi, Libya for 10,500 visitors. Being executed by two project managers and one site manager it took 40 assemblers five months to set up the stadium out of 1,150 tons of material. The material was supplied via 85 freight containers.
Besides a VIP area which is separated by glass and offers an extra access via a bridge, the football stadium in Benghazi is a permanent stadium and comes with 24 media-desks for press and TV, three camera towers and a separate platform for handicapped people. The stadium offers an ideal stadium-atmosphere due to completely closed corners, a FIFA redundant grandstand- and stadium-lighting as well as four floodlight-poles and a very modern BOSE stadium-PA-system.
Material import and local conditions imposed a rather special challenge upon realizing the stadium in Benghazi. Despite long waiting periods due to import delay NUSSLI planned and assembled the stadium within nine months.